Greetings to all owners!
The collection of unit key is based on apppointment and you can contact the management to set the date and time you want to collect the key once the loan is cleared and after you receive the letter from them (very soon).
The management office is allocating 15 minutes for each keys handover and settle some paperwork, frankly I do not think it's enough, but anyway it should be quick, because you don't have to submit your defects form on the spot. Instead, you can take your own time and take photos on the defects and submit to the management office/main contractor few days later.
Take your time on the defects. Pay more attention to the windows, door locks, loose plug-points. Overall the wall and ceiling finishings is okay. Maybe some uneven paint, which you can submit as defects as well.
From what I know, they will have to rectify the defects within 21 days, after acceptance by the main contractor.
Thank you!
Source: Robin Oh (Contractor)
NB: Robin Oh (Contractor): Do visit us at the clubhouse (Dewan), we have samples on cabinets, floorings, curtains, accessories, and real estate agent/bankers for sub-sales or to-let. Model showhouse hope to ready as soon as possible after handing over for owners to visit for complete renovation ideas.